Planning guide · England

Do you need planning permission for commercial solar?

For most commercial roofs in England, no. Rooftop solar on a non-domestic building is permitted development, and since November 2023 there is no megawatt cap on it. Here is what actually applies, what prior approval really tests, and the handful of cases where a full application is unavoidable.

Class J permitted development1 MW rooftop cap removed, Nov 2023Prior approval above 50 kW56-day determination

The short answer

Three facts settle most commercial roofs.

Class J
Rooftop is usually permitted development

Solar PV on the roof of a non-domestic building in England sits under Class J of Part 14 of the GPDO. Meet the conditions and no full planning application is required — the right is already granted.

No cap
The 1 MW rooftop limit is gone

The November 2023 amendment removed the old 1 MW generation limit on non-domestic rooftop solar. Your roof area, its structure and your load are now the real constraints, not a number in the legislation.

50 kW
Above that, prior approval

Installations above 50 kilowatts still need a prior approval application to the local planning authority. It is a much narrower, faster test than full planning — and the principle of the development is not reopened.

General guidance for England, current at July 2026. Permitted development rights differ in Scotland, Wales and Northern Ireland, and can be withdrawn locally by an Article 4 direction. Your local planning authority is the authority on your site, nothing here is a determination, and we always confirm the position in writing before design is finalised.

Questions

Straight answers.

Anything else. Call and speak to a director, not a sales team.

Do I need planning permission for solar panels on my commercial roof?

In England, usually not. Rooftop solar on a non-domestic building is permitted development under Class J of Part 14 of the GPDO, provided the equipment does not protrude more than 0.2 m beyond a pitched roof plane or sit more than 1 m above the highest part of a flat roof, stays 1 m back from the roof edge, is sited to minimise its effect on the building’s appearance and the amenity of the area, and is removed when no longer needed. Listed buildings and scheduled monuments are excluded, and an Article 4 direction can withdraw the right locally.

Is there still a 1 MW limit on commercial rooftop solar?

No. The Town and Country Planning (General Permitted Development etc.) (England) (Amendment) (No. 2) Order 2023 removed the 1 MW generation limit for solar on non-domestic buildings in November 2023. Large rooftop arrays can now proceed as permitted development, subject to the remaining Class J conditions and the prior approval requirement above 50 kW.

What is a prior approval application, and how long does it take?

It is a narrow consent check, not a planning application. For rooftop installations above 50 kW you apply to the local planning authority before starting work for a determination on whether its approval is needed for the design or external appearance of the development — in particular the impact of glare on occupiers of neighbouring premises. The authority has 56 days. It cannot use the process to reconsider whether solar should be there at all: permitted development has already settled that.

What about listed buildings and conservation areas?

A listed building sits outside Class J entirely: you need listed building consent, normally with planning permission, and the layout has to be designed around concealment. Conservation areas are different — rooftop solar can still be permitted development there since the 2023 changes, but design scrutiny is heavier and Article 4 directions are more common. On either, involve the planning authority early; months of programme are at stake.

Does the DNO grid application count as planning permission?

No — they are entirely separate. The G99 application to your distribution network operator (National Grid Electricity Distribution across the West Midlands) governs how much you may export and what protection is required. It has no bearing on planning, but it frequently sets the real programme: where local network headroom exists an offer can come back in weeks, and where reinforcement is needed it can run to many months. We apply early, in parallel with the planning route.

Does any of this apply outside England?

The permitted development rules described here are the English ones. Scotland, Wales and Northern Ireland each operate their own permitted development regimes with different thresholds. Wherever your site is, the local planning authority is the authority on it — this page is general guidance, not a determination.